No dramatic improvements to show for this week.  The plumbers came on Thursday and began the house plumbing.  We also did a 2 hour walk through with the electrician to verify and or change any electric/lighting needs.  He should be getting started this weekend. 
And for the barn, they did drop off some siding and insulation, they also did some more framing.  We are told it should be done by Monday.
 
 
 
 